If Anzacs are being laid up for lack of critical crew members, what is the point of an accelerated acquisition of ships that will inferior to the Hunters and, potentially, no better than the ANZACs?
If the constraint of suitably qualified and experienced personnel, any solution needs to include a pathway to build that side as well.
TBH from my POV the personnel issue/shortage is of greater concern than the need for an expanded Defence budget, if some of the proposed increases in warship builds were to actually happen. As significant and expensive as it might be to increase the budget by a few (or even several) tenths of a percentage of GDP, that can likely be done much faster and easier than increasing the number of needed specialists qualified to serve in key posts aboard a deployed warship
I would view Hobarts as a better platform than ANZACs, but agree not as good as Hunters. Perhaps there is an option to retire some of the first batch of ANZACs, cancelling their life extension, for some quickly made Hobarts built in Spain.
I would suggest the ANZACs have been laid up for a combination of staff shortages and bad condition, not just staff shortages.
I agree the recruitment side must be resolved and done so in the near term. I don't have any solutions here. I'm looking forward to what the announcement says about this.
It would likely be faster to accelerate the build of the
Hunter-class frigates and have the first vessels brought into service earlier to replace
ANZAC-class frigates than to have a yard start building "Hobart"-like vessels. It is no longer possible to have new/more
Hobart-class destroyers built as the three already in RAN service were. Systems and kit fitted aboard the current RAN destroyers are in some instances out of production. It might be possible to have new units built in a configuration similar to what the RAN destroyers will be like, post upgrade, but that will still take a number of years. In fact, even if a contract were signed for this tomorrow, it would likely be a year or IMO more likely two before the detailed design work would be finished so that first steel could be cut. There is also the issue of how long any new build would need in order to be fitted with Aegis, and/or SPY arrays. I have previously discussed some of the timelines involved and do not wish to re-hash all of that in this post, but we are talking about years needed to get the first vessel built and into service. IIRC first steel of the lead
Hunter-class frigate was cut last year, and construction is expected to be finished by 2029 followed by ~two years of testing and workups prior to commissioning in ~2031. First steel for prototype blocks was cut back in 2021 to test and validate construction methods. Also the first three frigates were ordered back in ~2018, which gave time for long lead items time to be ordered so that they can be fitted aboard the vessels whilst under construction.
If Australia were to make a request to purchase Aegis systems and SPY radar arrays from the US, it could easily be a year before the approval were to be granted which would then be followed by contracts getting signed before the systems could start getting constructed. I have mentioned this before, but it could easily be five or more years between decision to acquire a vessel using Aegis and the delivery of the Aegis components so that they could be fitted to a vessel under construction. I am aware of Spain having previously claimed to be able to deliver vessels to Australia by certain times, but I consider such times claimed to be dubious at best. IMO it is more likely that the times claimed would only be valid for minimally fitted out vessels, not some vessels which would be useful to the RAN.
Is it not possible to see Arrowheads enter service by 2029 if they cut steel next year? Less crew, more capable…
Type 31 cut steel 23rd September 2021 for entry into service 2025. 1 year drumbeat after FOC.
IMO unlikely, as I understand it the in service date for RN Type 31 frigates is now more like 2027 or 2028. One is looking at an in-service date some eight or nine years after they were ordered (15 Nov 2019) which had also been undergoing design work for a couple of years prior to the design getting selected and units ordered. If the RAN were to order some vessels to the Arrowhead 140 base design, there would still need to be some detailed design work done to fit the base design with systems the RAN wants or needs. If the RAN were to decide to pursue some development from the Arrowhead 140, then Australia would be starting a new design programme which would likely still need at least a year of work before things would be settled enough for contracts to get signed and orders placed, or if making a more direction comparison to the RN's Type 31 programme, Australia would likely be in a position similar to what the UK was in when the competitive design phase was launched back in 2018, ahead of the design getting selected, contracts signed and orders placed in 2019.
Again, as much as people might want or think that this can be rushed, certain things just take time to do.