my main concern is that this govt appears to have a higher focus on what Industry says rather than look at the fact that its the governance process which has been fundamentally responsible for delaying projects - and unfort both sides of Govt fail in wanting to accept the fact that its the way that the multi pass process has to be implemented via navigation of the various steering and oversight groups which blows things out.Lets hope he gets good military advice and not political horse$hit.
the reality is that the number of projects which can go through the mandated available review slots is 50% higher than whats avail - so you automatically have delays. The Divisions don't control the governance process but they pay the end price as far as public visibility is concerned - and ultimately the end user pays in the end.
its a bit rich blaming DMO, CDG etc when they inherit the process and have no capacity to change it. Progs like RPDE have no care and responsibility beyond providing an initial "give me this because I need it" but the funds to sustain and maintain then have to come out of someone elses hide. - and guess who gets grumpy then.....