On 21 April 2009, media reports, citing Pentagon sources, said that during 2007 and 2008, computer spies had managed to copy and siphon off several terabytes of data related to the F-35's design and electronics systems, potentially enabling the development of defense systems against the aircraft.[33] However, Lockheed Martin has rejected suggestions that the project has been compromised, saying that it "does not believe any classified information had been stolen".[34]
On 9 November 2009, Ashton Carter, under-secretary of defense for acquisition, technology and logistics, acknowledged that the Pentagon "joint estimate team" (JET) had found possible future cost and schedule overruns in the project and that he would be holding meetings to attempt to avoid these.[35] On 1 February 2010, Gates removed JSF Program Manager U.S. Marine Major-General David Heinz and withheld $614 million in payments to Lockheed Martin because of program costs and delays.[36][37]
On 11 March 2010, a report from the Government Accountability Office to United States Senate Committee on Armed Services projected the overall unit cost of an F-35A to be $112M in today's money.[38] In 2010, Pentagon officials disclosed that the F-35 program has exceeded its original cost estimates by more than 50 percent.[39] An internal Pentagon report critical of the JSF project states that "affordability is no longer embraced as a core pillar". On 24 March, Gates termed the recent cost overruns and delays as "unacceptable" in a testimony before the U.S. Congress. He characterized previous cost and schedule estimates for the project as "overly rosy". However, Gates insisted the F-35 would become "the backbone of U.S. air combat for the next generation" and informed the Congress that he had expanded the development period by an additional 13 months and budgeted $3 billion more for the testing program while slowing down production.[40] Lockheed Martin expects to reduce government cost estimates by 20%.[41]
In November 2010 as part of a cost-cutting measure, the co-chairs of the National Commission on Fiscal Responsibility and Reform suggested canceling procurement of the F-35B and halving orders of F-35As and F-35Cs.[42][43][44] At the same time Air Force Magazine reported that "Pentagon officials" are considering canceling the F-35B because its short range means that the bases or ships it operates from will be within range of hostile tactical ballistic missiles.[45] However Lockheed Martin consultant Loren B. Thompson said that this rumor is merely a result of the usual tensions between the US Navy and Marine Corps, and there is no alternative to the F-35B as an AV-8B replacement.[46] He also confirmed that there would be further delays and cost increases in the development process because of technical problems with the aircraft and software, but blamed most of the delays and extra costs on redundant flight test.[47][48]
The Center for Defense Information estimated that the program would be restructured with an additional year of delay and $5 billion in additional costs.[49] On 5 November 2010, the Block 1 software flew for the first time on BF-4 which included information fusion and initial weapons-release capability.[50] As of the end of 2010, only 15% of the software remains to be written, but this includes the most difficult sections such as data fusion.[51] But in 2011 it was revealed that only 50% of the eight million lines of code had actually been written and that it would take another six years and 110 additional software engineers in order to complete the software for this new schedule.[52]
In January 2011 Defense Secretary Robert Gates expressed the Pentagon's frustration with the skyrocketing costs of the F-35 program when he said "The culture of endless money that has taken hold must be replaced by a culture of restraint." Focusing his attention on the troubled VTOL F-35B Gates ordered "a two-year probation", saying it "should be canceled" if corrections are unsuccessful.[53] However, Gates has stated his support for the program.[54] Some private analysts, such as Richard Aboulafia, of the Teal Group state that the whole F-35 program is becoming a money pit.[53]
Former Pentagon manager Paul Kaminski has said that the lack of a complete test plan has added five years to the JSF program.[55] As of February 2011, the main flaws with the aircraft are engine "screech", transonic wing roll-off and display flaws in the helmet mounted display.[56]
The current schedule has the delivery of basic combat capability aircraft in late 2015, followed by full capability block three software in late 2016.[57] The $56.4 billion development project for the aircraft should be completed in 2018 when the block five configuration is expected to be delivered, several years late and considerably over budget.[58]
In November 2010, the GAO found that "Managing an extensive, still-maturing global network of suppliers adds another layer of complexity to producing aircraft efficiently and on-time" and that "However, due to the extensive amount of testing still to be completed, the program could be required to make alterations to its production processes, changes to its supplier base, and costly retrofits to produced and fielded aircraft, if problems are discovered."[59]
Delays in the F-35 program may lead to a "fighter gap" where America will lack sufficient jet fighters to cover requirements.[60] This gap may become even worse if Israel takes away fighters from the USAF to cover their own gap caused by the F-35 delays.[61] Australia may also seek to lease American fighters from the USN to cover their own capability gap in the face of F-35 delays.[62][63][64]
Initial Operational Capability (IOC) will be determined by software development rather than by hardware production or pilot training.[65]
In 2011 Carter said that the new $133 million price per aircraft was not affordable.