8-10 aircraft by 2010? I recall original plans for having ~12-24 aircraft by 2010. Are any aircraft going to be delivered this year? I mean "serial production" started 2 years ago, and earlier we were told that 10 aircraft are undergoing assembly right now. They're not going to be delivered until 2010? I knew NAPO was in pretty bad shape, but they did manage to get Su-24M2 modernizations done. I figured they should be able to do at least low rate production.
Yeah, u recalled correctly Feanor.
Vladirmir Mikhailov, then Commander in Chief of the Russian Air Force annaounced that the first operational wing would be fully equipped by
2010(455thbomber regiment in Voronezh).
He also added that 200 Su-34 would be procured by 2020..
Now this is't the case, it's incompatible with the planned slow production rate of between 8-10 aircraft per year. It also conntradicts a statement made by then the ministry of Defence, Sergey Ivanov who said:
"The state Armament Programme provides for purchasing 58 Su-34 by 2015"
To add further to the confusion, an official statement from Sukhoi Company says that:
"Within the 3 years contract between the MoD and Sukhoi until 2010, the Napo factory will produce and deliver 18 Su-34's.
Subsequently, the factory will deliver 8-10 Su-34 per year".
Now, to date non of these targets have been acheived.
Su-34 No.02 although officially delivered, was not actually completed and made the first flight several months later, and flew to Lipetsk on Aug 03 2007.
Su-34 No.01 followed the former prototypes and is currently being testet at the 929th GLIC in Akhtubinsk.
Not a singel Su-34 was build in 2007 or the first half of 2008.
My best guess is that the funding was not enough.. Maybe the aircraft proved more expensive than first anticipated.
NAPO have upgraded the existing Su-34's several times between 1993-2007.
Source: Piotr Butowski