So?, Rough timeline
Japan
2026 cut steel, 2029 delivery to RAN, 2030 service
2028 cut steel, 2031 delivery to RAN, 2032 service
2030 cut steel, 2033 delivery ton RAN, 2034 service
Australia
2029/2030 cut steel?, 2034/2035 delivery?(Probably around 5 years for the first?) 2035/2036 service?
Follow ons every 1 year(11 by 2042)?, 18months(11 by 2046)?, 2 years(11 by 2050)?
IMO the numbers for the Australian yard in WA are optimistic and likely overly so. One of my ongoing concerns with SEA 3000 is how optimistic some of these forecasts seem to be. One must remember that a proper warship construction yard in WA has yet to be built, which also means that an appropriately sized
and skilled workforce cannot be established yet either. It also means that there will likely be sharp limitations on what sort of work can be done prior to the completion of the frigate construction facilities which IIRC is expected for 2031. This likely means that the Australian yard cannot produce test blocks like Osborne has done for the
Hunter-class.
I would therefore anticipate that first steel might possibly get cut for the Australian-built GP frigates as early as 2029, they will not actually be laid down until 2031, though later dates for either/both are certainly possible. I would also expect the first Australian-built GP frigate to more likely commission into the RAN after ~seven years, not five. This would put things back to ~2038 for the fourth GP frigate entering RAN service. This number itself is a rough guestimate based off the times taken from Williamstown's construction of the two Australian-built
Adelaide-class frigates back at the end of the 80's into the early 90's.
Now I would also anticipate that once the project really gets going, so that the facility and workforce is established and operational, then a two year cycle to built a frigate could be reached. What I am much less certain on is how quickly a new facility and workforce could actually get to where it can manage such a build in two years. Looking back to the
ANZAC-class build from Williamstown, by the end of the programme there was about a three year timespan between a ship getting laid down and commissioning into the RAN and that was with a by then skilled workforce, having built a dozen frigates by the end (two
Adelaide-class and 10
ANZAC-class).
Now a new facility in WA might be built with greater capacity than Williamstown had, so that more hulls might be able to be worked on simultaneously, it will still take time for enough personnel to get recruited, trained and then skilled to make use of facilities fully. This in turn would likely mean that there might only be two or three Australian-built SEA 3000 frigates in RAN service by ~2040.
Therefore, I would expect Australia will need to do something in order to have a shot at keeping RAN surface fleet numbers up. IMO one of the potentially less risky options would be for Australia to order four to six frigates built in Japan, not just the three originally planned.