I think the important element at the moment is clarity about how far the SSN programme has got noting it is supposed to be ahead of schedule. The Astute situation may offer advantages in that the tooling and set up for the construction will be available after Agincourt allowing that to be transferred to Australia or used in situ to start hull 1. The hull is not the biggest issue (noting we would have been building a similar sized hull with the Attack) the big issue is the reactor noting the PWR-2 is basically out of production. So do we get an Astute with a US reactor. The time frame for reactor delivery will drive the entire programme. The drumbeat for the Virginia (depending on blocks) ranges from two to four years. With two hulls in build at any one time then less than 2 years 'may' be practical the build way is set up. if Australia is to be supported by the UK and/or the US I would hope it would not take 20 years to get the first boat in the water.I get that, I should clarify, LOTE should go ahead regardless, for all subs. I don't think anyone is serious arguing against that anymore. But that is still 12 + years with reduced capability, shrinking crew numbers, if everything goes to plan.
50 or 60 year old subs, are going to have issues beyond just meeting metal fatigue requirements, even with a refit. Those subs are 20+ years old now. Collins turns 30 in 2026 - from its commissioning date. That represents a generation, in terms of construction, operation and more than that in design. Those that built the Collins (and its capabilities) are now progressing into the later part of their careers and retiring out.
I guess people would feel more relaxed and trusting if there was a solid well planned timetable we were all working towards, and that all the puzzle pieces fitted together. People have deep fears about the current state of the world and Australia's ability to plan and implement as massive program to deal with it.
While we look at SSN's as just a homogeneous grouping, that will be our holy land and saviour, SSN's have their challenges too. The timing isn't exactly sweet.
Astute program is basically finished, Agincourt is really the only one left with any significant work to go, even then its four years in and its supply line dry and converting to ssbn or withered. Virginia is rumoured to end after block V. US and UK are turning to focus on SSBN. Astute has lots of issues for a build, Virginia like nearly all US programs has a significant crew demand. US ordered to laid down dates are often 5-10 years with say an approximate build of ~ 5 years. Our first SSN if ordered today, could very well be a 20 year gap before commissioning. Then we would need to spit out a SSN every 1-2 years to match the Collins class aging out.
Peter Briggs argues that is not just the first ssn we need to worry about. Its about when we have a fully operational SSN force and when that will happen.
Australian-built evolved Collins needed to bridge the gap to nuclear subs | The Strategist
I should start by affirming my support for Australia’s transition to nuclear-propelled attack submarines, or SSNs, as my detailed study, delivered to the Department of Defence in 2013, and my public advocacy implies. I think ...www.aspistrategist.org.au
Also I am not trying to push a wheel barrow here. I don't build subs. But I think it is worth having a detailed academic discussion regarding it. It may end up being inappropriate to build son of Collins, but not inappropriate to continue its development as a plan B until plan A is actually happening.
I can certainly understand what a lot of old salty submariners are talking about.
Construction of the ASC facility in 1987 with Collins commissioned in 2006 (6 years in construction after being laid down in 2000 and launched in 2003). I would hope a mature design would prevent the issues had with Collins (which only existed on paper before hand) which delayed its construction. Construction of the new ASC facility has commenced with some parts already done. I cannot get a status out of the ANI website but it does indicate that some of the facilities have been completed. Work is on hold until the SSN programme is worked out.
220330-The-Morse_Web.pdf (ani.com.au)
Timing is everything and proposing a Son of Collins with no clear idea of the timing ... which in itself is based on the design decision is fraught with problems. The Son of Collins will not be a copy of the original if it goes ahead and setting up for it may well adversely impact the SSN programme. Some of the jockeying about is essentially proposing a new design which would be lucky to be delivered by the time hull 1 of the SSN is built. We are getting a larger defence budget but I don't see two submarine programmes being adopted unless we cut in other areas.
The problem is we do not have the information in the public domain to make a call. I agree the government need to get a wiggle on and its a pity it took this long for bipartisan support. I do not see the Collins living on until it is 60