Parliamentary transcript from the Senate Estimates last Wednesday, gives some insight into LAND 400.
Phase 2 will be decided by late February 2016 and remains at 225 wheeled vehicles.
Phase 3 will see a minimum of 450 tracked vehicles with first pass approval hoped for 2016.
more LAND 400
Senator CONROY: Back in budget estimates, at that time General Caligari confirmed that phase 3 would be around 500 vehicles. In other words, if we take the 700 and subtract the 225 that would be acquired under phase 2, we are looking at around 500 vehicles to be acquired in phase 3. Does that remain the case?
Major Gen. McLachlan: In the order of that number, yes.
Senator CONROY: So we are still planning to acquire about 500 vehicles under LAND 400 phase 3. Is the government committed to that figure. Is that still the publicly available figure?
Major Gen. McLachlan: That is the publicly released figure that was in the previous DCP. Clearly, we are now waiting on the white paper to confirm those numbers.
Senator CONROY: I have heard a rumour it could be as low as 450 vehicles.
Major Gen. McLachlan: Once again, it is dependent on the white paper.
Air Vice Marshal Hupfeld: The figure was for a minimum of 450. That is what is being considered at the moment. This will be refined through the force structure review and the integrated investment program, when that is released. We are still doing the analysis on the outcomes of that, linked to follow the 225 that are currently foreshadowed for phase 2. Obviously, that is still under the tender negotiations, so we cannot provide any additional analysis on that at the moment.
Senator CONROY: Does Defence have a date when it plans to start the tender process for phase 3?
Air Vice Marshal Hupfeld: We do have some plans on that, but we have yet to initiate the project formally. We plan to initiate it early next year and we expect it will undergo the first principles review process and be one of the first projects that will undergo the new capability development life cycle.
Senator CONROY: Has the government agreed to a commencement date for phase 3? Or is that part of the white paper?
Air Vice Marshal Hupfeld: That is part of the white paper and the integrated investment program.