Ooops! Brain fart. Mixing up me old & new tankers.
My fault, I fluffed it first
Ooops! Brain fart. Mixing up me old & new tankers.
Also won't hurt the RAN too!
From another forum I visit,
The Defence Secretary has announced the steel cut for new Type 26 frigates will be in summer 2017, subject to final contract negotiations
https://www.gov.uk/government/news/defence-secretary-confirms-summer-start-for-type-26-frigates
Indeed. Got a mate on board QE, hoping to hear good things. They have been told to expect fire alarms and so forth however. Normal part of workup.
Considering the pressure they've been under to announce a date they wouldn't have announced the intention if they weren't fairly convinced of it, a 3 month window is a reasonable timeframe to say 'about then'. I wouldn't be overly concerned about it considering the attention it has received in both worlds.
Oh crikey I'm under no illusion that they are under immense pressure to get the ball rolling, they will want to be pretty confident that they will but it wasnt that long ago that they could not even say when still will be cut from budgetary and contract reason.
I hope they do kick on when they say but I would not be announcing anything till the hade a signature on a document, it just seems to me that they are creating their own problems for a short to gain it takes pressure of BAE and it's now all on goverment to get the project moving in the time frame listed, and what happens if they can't agree?
Hi,
What are peoples thoughts on the impending removal or harpoon from service with out funded replacement.
Despite the 1c versions age, it seems madness to me to not have some form of anti ship missile throughout the fleet.
Additionally, with increased russian naval activity through and close to British waters, seems clear to me that we need to maintain as high a number of dedicated t23 asw units in and around the uk. This can be helped by deploying t45 to kipion, as fres, to the med as we saw recently with diamond, or should we send anything south.
However, without wanting to play fantasy fleets, with the increasing sub threat isn't there an increasing pressure to perhaps scrap the t31 and go with a full build of asw t26?
And to aid this and i realise we cant just grow money on trees, but if tommahawk were added to t45, we could perhaps stop gap the sub east of suez as our response to potential land strike that may be required to allow for more assets in the north sea/baltic and north atlantic regions
Cheers Sellers
But only eight of those 13 hulls would have had towed sonar arrays, & thus been fully equipped for ASW. We're getting the same high-end ASW capability.
But it is glaring obvious that the UK needs more 1st tier ASW hulls as the original order was 13 from memory with the only only reason of there demise being budgetary along with the cut in numbers to the T45 Destroyer program, I also think the UK sold themselves short with only 7 Astute submarine
Given the financial pressures the RN is facing, one has to wonder whether the two QE carriers were the way to go? Not sure if two 30-40,000 ton vessels would have been all that less expensive. Giving up the nuclear deterrent would allow more Astute subs in lieu of Successor boomers. The former would be more useful but if the UK feels nuclear deterrence can't be outsourced then something had to give, first it was the Darling reduction and now the Type 26 ( and probably the Type 31).
Asked by Douglas Chapman
(Dunfermline and West Fife)
Asked on: 01 November 2016
Ministry of Defence
Royal Fleet Auxiliary
51473
To ask the Secretary of State for Defence, what the principal technical faults are that have led to the delay of the transfer of the RFA Tidespring to the UK for customisation and capability assessment trials until 2017.
A
Answered by: Harriett Baldwin
Answered on: 08 November 2016
Delays in finalising elements of electrical design and the installation of Multi-Cable Transit insulation in accordance with new legislative regulations resulted in some adjustments in the build schedule. These issues have now been resolved and Tidespring is expected to arrive in the UK in early 2017 to begin UK customisation and capability assessment trials.
Notwithstanding these issues, which are not unusual for any First of Class ship, build of the remaining ships in the Class is progressing well and we remain confident that all four tankers will be in service with the Royal Fleet Auxiliary by the end of 2018, as planned
Hi,
What are peoples thoughts on the impending removal or harpoon from service with out funded replacement.
Despite the 1c versions age, it seems madness to me to not have some form of anti ship missile throughout the fleet.
Additionally, with increased russian naval activity through and close to British waters, seems clear to me that we need to maintain as high a number of dedicated t23 asw units in and around the uk. This can be helped by deploying t45 to kipion, as fres, to the med as we saw recently with diamond, or should we send anything south.
However, without wanting to play fantasy fleets, with the increasing sub threat isn't there an increasing pressure to perhaps scrap the t31 and go with a full build of asw t26?
And to aid this and i realise we cant just grow money on trees, but if tommahawk were added to t45, we could perhaps stop gap the sub east of suez as our response to potential land strike that may be required to allow for more assets in the north sea/baltic and north atlantic regions
Cheers Sellers
On your last point, we should fit the Type 26 with the US Mk41 VLS so that they can carry Tomahawk thus releasing our submarines for ASW and anti-surface missions. I doubt we will though. I'm prepared to bet that they enter service Fitted For But Not With a strike VLS capability.
Furthermore, we don't intend to fit a long range ASM to the F35 so our carriers would have no anti surface strike capability without sending the F35 into the envelope of any surface vessel equipped with an area defence SAM.
As for paying for useless patrol boats, the alternative was to not buy them and have BAE sack a large portion of the workforce only to then re-hire and ramp up with inexperienced people to start building Type 26 which is under budgetary scrutiny already. I don't think it's neccesarily a bad trade off overall to keep the people who make their living by building warships on staff when the next big project comes through.
As I understand it, and I stand to be corrected, we had agreed a sum of around £200m to keep the yard workers employed during the shipbuilding gap even if there was nothing for them to do in order to preserve the skill base. We have then forked out around £150m on top of this for three useless patrol boats that duplicate capabilities we already have. I think we have also ordered a further two (at what cost I don't know) due to T26 delays.
You are unfamiliar with the TOBA, it was (AFAIK) specifically stated that ship build/support work of the value of £230m a year would go to those yards. It was not MOD sliding over a pile of money just to keep people on staff.
I don't like the design either, but the sarcastic way you described 'skewed priorities' (to me) read as though they didn't have a contractual obligation to give the yards something to do.
How long would a new design have taken, vs. the tweaked old design we got?