Last patrol ships due for delivery
By HANK SCHOUTEN - The Dominion Post
Last updated 05:00 03/12/2009
The navy will finally take possession of two new offshore patrol ships next year, two years after they were due in service.
The ship builder must run one more test before the $90 million ships, HMNZS Otago and Wellington, are handed over.
They were expected to be delivered to Auckland in January or February, Defence Minister Wayne Mapp said yesterday.
The ships are the last of seven ships built under the $500 million Project Protector contract. They should all have been in service two years ago.
The multi-role HMNZ Canterbury was the first to be commissioned, but it was beset with problems. An independent report last year estimated modifications would cost $20 million.
The contract was awarded to Australian shipbuilder Tenix Defence in 2004. BAE Systems Australia, which later took over the company, has been involved in lengthy talks to sort out design and safety problems. It is understood that it is costing BAE more than $50m to fix problems with the new fleet.
A flaw with the system that launched inflatable seaboats from the patrol ships led to the death of Able Seaman Byron Solomon, 22, who drowned when the inflatable boat he was on capsized in 2007.
Dr Mapp said a final test would be carried out this month to see if inflatable boats could be launched safely while the ships were travelling at about five knots.
"People are confident that the test is going to work OK, but they need to see, given what happened to Able Seaman Solomon."
BAE had also solved a problem with the weight of the ships, which meant an ice-strengthening band was too low in the water to protect the hulls from Antarctic ice damage.
Some other problems were still subject to mediation, but Dr Mapp said he was happy with the way they had been dealt with so far.