Yes - happening progressively across the fleetOn RAN colour scheme - is there a program to move to a darker shade?
Looking down on Garden Island the ANZACS (assuming painted more recently post refit) look a lot darker?
Not critical - just wondering...
Ben
Nope, they based the contract on the used the original BPC build contract which specified those colours and I understand there was a cost difference changing. I would not discount the comment by Assail in this regard either as these vessel are a short term fix while the ACPB have remediation work done and to replace HMAS Bundaberg which was destroyed by fire.I don't know why they didn't spring for some grey paint.
Perhaps there is some sort of convention that only naval vessels get to sport the Haze Grey.
Thanks MB - appreciate it.Yes - happening progressively across the fleet
MB
A 4th Hobart has been off the table for at least 3 years, not an option at all. Lead in requirements shut down long ago, and the time to activate that again would be way too long, IIRC, it was close to 4 years ago just to get the combat system/Aegis etc.Construction of the new frigates for the RAN could be delayed until 2022 ... at least according to Andrew Davies.
https://www.aspistrategist.org.au/future-frigates-not-fast/
He actually makes a good point in that it does seem to be very ambitious to have first steel cut within a couple of years of the design being selected.
With the Hobart class the initial design was selected back in 2007 and construction didn't commence until 2012. The Anzacs were selected in 1989 with construction commencing in 1993. So it would seem that history is against this happening.
The best chance of an early build would be if the the modified Hobart proposal got the nod.
It might be sensible to come up with a plan B just in case there are delays in this program. Perhaps a fourth Hobart might not be off the table.
Except that in the case of the evolved F105 the historical AWD time line is not a good bench mark as the hull form of he AWD and the evolved vessel is the same and the hull modules are not significantly different. What the timeline does do is give the F105 a theoretical advantage, however, the winding down of work with the yards that built the modules may delay start up a bit.Construction of the new frigates for the RAN could be delayed until 2022 ... at least according to Andrew Davies.
https://www.aspistrategist.org.au/future-frigates-not-fast/
He actually makes a good point in that it does seem to be very ambitious to have first steel cut within a couple of years of the design being selected.
With the Hobart class the initial design was selected back in 2007 and construction didn't commence until 2012. The Anzacs were selected in 1989 with construction commencing in 1993. So it would seem that history is against this happening.
The best chance of an early build would be if the the modified Hobart proposal got the nod.
It might be sensible to come up with a plan B just in case there are delays in this program. Perhaps a fourth Hobart might not be off the table.
Apparently Defence has issued a statement confirming that the ships were maintained and operated in accordance with the builders' specifications, including the oils and lubricants used in their operation.Has anyone any more info on the pod problems on the LHDs?
Apparently Defence has issued a statement confirming that the ships were maintained and operated in accordance with the builders' specifications, including the oils and lubricants used in their operation.
Looks like they might be shifting the blame to Navantia.
https://www.defenceconnect.com.au/maritime-antisub/637-shipbuilder-faces-uncertainty-for-ffp-bid
This next statement is completely unsubstantiated. But......Apparently Defence has issued a statement confirming that the ships were maintained and operated in accordance with the builders' specifications, including the oils and lubricants used in their operation.
Looks like they might be shifting the blame to Navantia.
https://www.defenceconnect.com.au/maritime-antisub/637-shipbuilder-faces-uncertainty-for-ffp-bid
And likely irrelevant to the issues anyway, unless they've somehow morphed from electric azipods, or the engine problems have nothing to do with what has been reported (and discussed here)This next statement is completely unsubstantiated. But......
I mate of mine was on a plane heading out of Sydney the other day and sat next to an oil company guy. The conversation about the LDH's kicked off and this oil guy mentioned that the fuel oil supplied to the ships was contaminated somehow and there is now metal filings throughout the engines on both ships.
Like I said unsubstantiated.....
The Spanish only operate Juan Carlos for like 40 or 50 days a year, where we have operated Canberra for well over 200 days a year. We are pretty much the lead operator of this class of ship now, the Spanish will be learning of any emergent issues off of us.I guess Navantia will be leaning on Siemens, the POD subcontractor. Tried to find out if the Juan Carlos had any POD issues but didn't find any. Several cruise ships have had problems with other POD manufacturers though.
+1The Spanish only operate Juan Carlos for like 40 or 50 days a year, where we have operated Canberra for well over 200 days a year. We are pretty much the lead operator of this class of ship now, the Spanish will be learning of any emergent issues off of us.
Given the tight schedule for production of the future frigate and potential for delay, I wonder what sort of life is left in the remaining Adelaide class?Construction of the new frigates for the RAN could be delayed until 2022 ... at least according to Andrew Davies.
https://www.aspistrategist.org.au/future-frigates-not-fast/
He actually makes a good point in that it does seem to be very ambitious to have first steel cut within a couple of years of the design being selected.
With the Hobart class the initial design was selected back in 2007 and construction didn't commence until 2012. The Anzacs were selected in 1989 with construction commencing in 1993. So it would seem that history is against this happening.
The best chance of an early build would be if the the modified Hobart proposal got the nod.
It might be sensible to come up with a plan B just in case there are delays in this program. Perhaps a fourth Hobart might not be off the table.
I would have thought that their replacements are the AWDs, not the new frigates. With the first of those likely to be commissioned in the relatively near future I suspect Darwin's not too distant future is as a dive wreck, not a bandaids and baling twine place holder.Given the tight schedule for production of the future frigate and potential for delay, I wonder what sort of life is left in the remaining Adelaide class?
With HMAS Darwin the sole remaining FFG of the original batch of 4 one would guess there is not too much life left in her, however the two younger ships HMAS Melbourne and Newcastle should still have some potential to "soldier on".
Maybe these last two FFG's might remain in service well into the 2020's.
I guess it will all depend on how well both the OPV and future frigate schedule pans out.
Time will tell
Regards S
Darwin is scheduled for Decommissioning end of this year, Melbourne next year and Newcastle 2019. Any delays in the production of the future frigate won't change this. Despite what the AWD's/DDG's were originally envisioned to replace they are now replacing the FFG's and the FFG's will be decommissioned as the AWD's/DDG's are commissioned.Given the tight schedule for production of the future frigate and potential for delay, I wonder what sort of life is left in the remaining Adelaide class?
With HMAS Darwin the sole remaining FFG of the original batch of 4 one would guess there is not too much life left in her, however the two younger ships HMAS Melbourne and Newcastle should still have some potential to "soldier on".
Maybe these last two FFG's might remain in service well into the 2020's.
I guess it will all depend on how well both the OPV and future frigate schedule pans out.
Time will tell
Regards S
Thanks for the reply.Darwin is scheduled for Decommissioning end of this year, Melbourne next year and Newcastle 2019. Any delays in the production of the future frigate won't change this. Despite what the AWD's/DDG's were originally envisioned to replace they are now replacing the FFG's and the FFG's will be decommissioned as the AWD's/DDG's are commissioned.
I wouldn't be surprised if once the decision is made to build three F-105 based frigates (with Aegis, two helos). I would imagine things will move pretty fast. I don't see it taking as long as the AWD's. I would imagine the government would be taking steps to accelerate things as quickly as possible. You are talking about building the same basic ship hull down.Darwin is scheduled for Decommissioning end of this year, Melbourne next year and Newcastle 2019. Any delays in the production of the future frigate won't change this. Despite what the AWD's/DDG's were originally envisioned to replace they are now replacing the FFG's and the FFG's will be decommissioned as the AWD's/DDG's are commissioned.