Full-pace, full-scope testing of the Joint Light Tactical Vehicle prototypes began Sept. 3 and will last for 14 months.
Each of the three vendors — Oshkosh Defense, Lockheed Martin and AM General — delivered 22 vehicles and six trailers for testing to three sites — Aberdeen Proving Ground, Md.; Yuma, Ariz.; and Redstone Arsenal, Ala.
Rigorous reliability testing over various terrains and in different weather conditions and protection-related testing is being conducted, said Col. John Cavedo, the Joint Program Office manager, who spoke Sept. 4, during a JLTV webcast.
The program is still on track despite this year’s sequestration and the continuation of continuing resolutions, but if budget issues are not resolved by next year, Cavedo said he could not rule out a slip in the schedule.
“We’re doing everything we can to keep the program on track,” he said, emphasizing the importance of the program to meeting asymmetrical threats like those experienced in Iraq and Afghanistan.
CLOSING CAPABILITIES GAP
Cavedo related an incident years ago at the Fulda Gap on the East-West German border.
“My company commander pointed to the northeast and told me ‘that’s where the enemy will come from,’ and then turned around and said, ‘that’s the secure area in the rear where the friendly forces will be.'”
During Cold-War-era exercises, Humvees safely moved about the rear area while tanks and other heavily armored vehicles would maneuver in the battle space. The Fulda Gap was considered by many to be the best line of approach for Soviet tanks moving west and south.
That notion of front lines and rear area was no longer applicable after 9/11, he said. Humvees became vulnerable to improvised explosive devices no matter where they were. Up-armor was added for protection but the enemy adapted to that with more lethal explosives.
The added weight of the up-armor taxed the Humvees’ performance and further limited its payload, which now included network gear. And, the Humvees were just getting old, with the first ones rolling off the assembly line about three decades ago.
Soldiers and Marines continued to be vulnerable, so the mine-resistant, ambush-protected vehicles, known as MRAPs, were developed. These had good payload and protection and helped save many lives over the last six years, but performance was sacrificed and Soldiers could not move with speed and agility around the battlefield, especially in the difficult terrain in parts of Afghanistan, he said.
Furthermore, the heavier versions of the earlier MRAPs could not be moved around the battlefield by helicopter and required strategic lift, which in turn required adequate runways for these big cargo planes to take-off and land.
The sustainment cost for the MRAP program increased over time, he said, as more variants were developed by different vendors. Parts were not interchangeable and mechanics had to get follow-on training, he said.
The JLTV closed the capability gap, addressing “the iron-triangle of payload, performance and protection,” he said. Its payload and protection is similar to an MRAP and its performance exceeds that of a Humvee.
ADAPTABILITY & FLEXIBILITY
Besides addressing the “iron-triangle,” Cavedo said the JLTV is designed to meet the needs of the commander for a variety of missions.
The commander can decide what level of protection JLTV needs for the mission, he said, pointing out that armor kits will be available for vehicles going into harm’s way. Also, some of the JLTVs will be equipped with heavy weapons, including TOW missile systems, while others can be used as light, utility vehicles.
Other kits include command and control and network gear. He said JLTV “plug and play” open-architecture technology allows for future networks and electronic devices to be installed without a vehicle redesign.
While different vehicles will have different kits, all vehicles come equipped with automatic fire extinguishers, multiple egress options, fuel-tank fire suppression systems and combat locks.
Powering the 21,000-pound gross weight JLTV and whatever kits and trailers are added on is a 300-horsepower fuel-efficient diesel engine. JLTVs also will be able to tow the thousands of legacy trailers that are still useable.
HOLDING COSTS DOWN
“We’ve managed to hold cost down by promoting better competition between vendors, incentivizing productivity and conducting an analysis of alternatives,” he said. By “analysis of alternatives,” he means ordering the right number of kits and mission packages. “We don’t want surplus kits stockpiled in warehouses across the country.”
Incentivizing productivity, he explained, means that after giving the original equipment manufacturer, or OEM, the specs, like protection, speed, weight and so on, it is up to them to determine how it’s built and what the tradeoffs are.
He provided an example. Besides armor kits, the basic JLTV requires a certain level of protection, he said. There might be very exotic metals out there that are lightweight and offer exceptional protection, but the cost involved would be astronomical. So a tradeoff might be reached where steel or aluminum is used to keep the cost down but still meet the basic requirements. To be competitive, however, the thickness or type of material used might exceed basic standards but be within a reasonable price range.
Tradeoffs like this apply to the power and transmission features and to everything else on the vehicle, he said. They’re trying to be as innovative and competitive as possible with the other OEMs, yet they must stay below the $250,000 assembly-line figure.
There are other ways cost has been controlled. Instead of requiring each OEM to supply 35 vehicles, they were required to provide 22 for the testing phase, he said. That number is reasonable and adequate for an effective evaluation.
Also, instead of a cost-plus type contract, the JLTV is on a firm-fixed price contract.
“In the past, the production price was set after down-select,” he said. “Our intent was to set production prices during competition so as we go forward into the competitive down-select we’ll have production prices set at that point and not negotiated for the years out.”
TIMELINE
Source-selection evaluation will start in early 2015, and conclude by July of that year when a single vendor will be selected.
At that time, 2,000 vehicles will be produced and be tested for three years with the focus on fine-tuning the assembly line, full-up system testing and so on.
Full-scale production will begin in fiscal year 2018 with the ratio of organic to contract work determined by the third quarter of fiscal year 2015.
By 2018, the first Army brigade will roll with new JLTVs, he said.
Production will total 49,000 JLTVs for the Army and 5,500 for the Marines, with the production cycle ending sometime in the 2030s.
Kits will initially be produced by the selected OEM but follow-on kits might use a different vendor, he said.
In conclusion, Cavedo said the JLTV comes at the right time at the right cost, and is the perfect match to the Army’s shift to the Pacific, regional alignment strategy and meets the requirements of the Defense Strategic Guidance of 2012 and the Army’s 2014 Equipment Modernization Plan.