US Department of Defense, The Department of Defense has released details on major defense acquisition program cost and schedule changes since the June 2005 reporting period. This information is based on the Selected Acquisition Reports (SARs) submitted to the Congress for the Sept. 30, 2005, reporting period.
SARs summarize the latest estimates of cost, schedule, and technical status. These reports are prepared annually in conjunction with the President's budget. Subsequent quarterly exception reports are required only for those programs experiencing unit cost increases of at least 15 percent or schedule delays of at least six months. Quarterly SARs are also submitted for initial reports, final reports, and for programs that are rebaselined at major milestone decisions.
The total program cost estimates provided in the SARs include research and development, procurement, military construction, and acquisition-related operation and maintenance (except for pre-Milestone B programs which are limited to development costs pursuant to 10 USC 2432). Total program costs reflect actual costs to date as well as future anticipated costs. All estimates include anticipated inflation allowances.
The current estimate of program acquisition costs for programs covered by SARs for the prior reporting period (June 2005) was $1,474,049.4 million. There was a net cost increase of $64,999.4 million (+4.4 percent) during the current reporting period (September 2005), which was due primarily to cost increases associated with the four-year stretchout and restructure of the FCS program.
CURRENT ESTIMATE (in $ millions)
— June 2005 (85 programs): $ 1,474,049.4
— September 2005 (85 programs): $1,539,048.8
Net Cost Change: +$ 64,999.4
For the September 2005 reporting period, there were quarterly exception SARs submitted for thirteen programs. The reasons for the submissions are provided below.
ARMY:
–ACS (Aerial Common Sensor) – The SAR was submitted to report schedule slips of at least six months due to sensor integration challenges on the selected platform resulting in space, weight, power, and cooling issues. There is currently a ninety-day contract stop-work order in place. Alternative solution sets are being investigated. Impacts to performance and cost are not known at this time.
–ARH (Armed Reconnaissance Helicopter) – This is the initial SAR submission following approval to proceed into System Development and Demonstration (Milestone B) on July 26, 2005.
–ATIRCM/CMWS (Advanced Threat Infrared Countermeasure/Common Missile Warning System) – The SAR was submitted to report schedule delays of more than 30 months for ATIRCM Initial Operational Test and Evaluation (IOT&E), First Unit Equipped, and Full Rate Production (FRP). The delays are due to CMWS acceleration and ATIRCM performance and reliability issues which resulted in separate IOT&E and FRP decisions. Program costs decreased $8.1 million (-0.1 percent) from $4,717.0 million to $4,708.9 million, due primarily to acceleration of the A-Kit (installation kit) buy by three years.
–FCS (Future Combat Systems) – Program costs increased $62,541.4 million (+63.3 percent) from $98,878.6 million to $161,420.0 million, due to program restructure (+$54,270.6 million) and extension of schedule by four years (+$8,270.8 million).
–JLENS (Joint Land Attack Cruise Missile Defense Elevated Netted Sensor System) – This is the initial SAR submission following approval to proceed into System Development and Demonstration (Milestone B) on August 5, 2005.
NAVY:
–CVN 21 – The SAR was submitted to report a schedule delay of the Defense Acquisition Board (DAB) program review from June 2006 to July 2007 because of a delay in the funding of the lead ship (CVN-78). There were no cost changes reported.
–DD(X) – The SAR was submitted to report schedule slips of seven months in the decision to approve System Development and Demonstration (Milestone B) and nine months in the Lead Ship Award date. The Milestone B is currently scheduled for November 2005 and the Lead Ship Award date is planned for January 2006. Both events slipped due to continuing resolution of the DD(X) acquisition strategy. There were no cost changes reported.
–H-1 Upgrades – The SAR was submitted to report a schedule slip of eight months (from January 2006 to September 2006) in the completion of Operational Evaluation (OPEVAL) Testing. This slip was due to delays in completing aircraft block modifications and Helmet Mounted System Display (HMSD) issues. Incremental improvements to the HMSD are being made to address the issues. Program costs increased $28.3 million (+0.4 percent) from $8,004.5 million to $8,032.8 million, due primarily to an increase in RDT&E for studies and analyses (+$10.8 million) and additional procurement funds for UH-1Y Government Furnished Equipment and recurring costs (+$17.5 million).
–LHD 1 – This is the final SAR for the LHD 1 since it is more than 90 percent expended. The program began in 1981 and has now delivered 6 of 7 ships to date. The final ship, LHD-8, is under construction and is scheduled to be delivered in July 2007. Program costs decreased $49.9 million (-0.5 percent) from $10,001.2 million to $9,951.3 million, due primarily to revised actual costs.
AIR FORCE:
–F/A-22 – The SAR was submitted to rebaseline from a Development to a Production Estimate following the April 2005 approval of Full Rate Production (Milestone III). There were no cost changes reported.
–NPOESS (National Polar-Orbiting Operational Environmental Satellite System) – The SAR was submitted to report an increase in the Average Procurement Unit Cost Program (APUC) of 15 percent or more (Nunn-McCurdy unit cost breach). Congress was notified September 28, 2005, of the breach. Program costs increased $1,485.2 million (+21.8 percent) from $6,800.0 million to $8,285.2 million, due primarily to technical issues arising during the engineering and manufacturing development portion of the program. The NPOESS Tri-Agency Executive Committee (EXCOM) has directed that an Independent Program Assessment team review the program and provide recommendations for replanning options. The EXCOM is expected to approve a restructure of the program during December 2005.
–SBIRS (Space Based Infrared System) High – The SAR was submitted to report increases in the Program Acquisition Unit Cost and Average Procurement Unit Cost of 15 percent or more (Nunn-McCurdy unit cost breach). Program costs increased $1,024.8 million (+10.7 percent) from $9,613.3 million to $10,638.1 million, due primarily to a revised estimate of development and production costs and the addition of program office operating costs to complete production of GEO 3-5.
–WGS (Wideband Gapfiller Satellites) – The SAR was submitted to report schedule slips of six months or more. The Initial Operational Capability (IOC) slipped from May 2007 to March 2009 and Full Operational Capability (FOC) has been revised to a
Iraq accuses Israel of seeking pretext for future attack
Iraq has accused Israel of attempting to legitimize an attack on its territory, after the Israeli foreign ministry protested to...